I would appreciate some hep with a calculation stemming from the downtime problem this past week.
I put my steel coffin in at 11 AM local time last Tuesday. My initial calculation was that it should come out no later than 12 noon today. Then there was downtime which I figured has added a minimum of 10 hours. So the coffin should come out about 10 PM tuesday local time. However the coffin now shows 95% complete at 8:30 PM Tuesday local time.
So has anyone calculated how much time is needed to complete 5% of the coffin cementation? Thanks for any help.